SBS Group - The Langdon Project

SBS Group* completes large-scale LGS framing project in Winston Hills, NSW

SBS Group - Langdon - Frames made from TRUECORE® steel

Project details


Project

The Langdon Project


Location

Winston Hills, NSW



Show more

The SBS* system made from TRUECORE® steel saved approximately two months on the construction program and associated preliminaries.


  • Fast and efficient installation

  • Overall construction time reduced

  • Lightweight and easy to move around

  • Strong and dimensionally accurate

  • High tech modelling

To deliver a three-level apartment development on top of an existing shopping centre.

Project Goal

Summary

SBS Group (now trading as Cortek) has successfully completed a three-storey apartment addition on top of an existing busy shopping centre. Engaged from the design stage by Hamilton Marino Builders, the SBS system made from TRUECORE® steel saved approximately two-months on the construction program and associated preliminaries.

Key Challenges

  • The shopping centre is located on a busy street and remained fully operational throughout construction.

  • A firm deadline and tight program for completion.

Key Benefits Delivered

Speed

The SBS frame structure was designed in a way to allow follow-up trades faster access to site. (NG)

The lightweight design was easier to install than a conventional concrete or timber structure, resulting in a faster build and install. (TJ)

Efficiency

The prefabricated system resulted in fewer deliveries needing to be coordinated within the busy shopping area. (NG)

Integration

SBS Group was engaged in the design stages of the project which allowed them to help facilitate the complete engineering solution of light-weight framing. (TJ)

The shop drawings from SBS Group were coordinated with windows and joinery shop drawings to help to eliminate design clashes. (TJ)

Outcomes

In summing up the project, Tim James, of Hamilton Marino Builders said that “By using the SBS Group System, we estimate that we have saved approximately two months of construction program and associated preliminaries”.

SBS Group expands on this.

“We addressed the challenges faced by the builder by using, our BUILD SMARTER approach through the design stage from initial concept through to delivery. Working hand in hand with the builder and ensuring that the frames were delivered and designed in such a way as to allow the installer to install effectively and allow the follow-on trades on site quicker.”

Roger Weeks
Operations Manager at SBS Group

Of the selection of TRUECORE® steel, Roger Weeks from SBS Group continued, “I consider [TRUECORE® steel] to be an industry standard in LGS framing and a project of this scale demanded quality materials and processes.”

Sources

  • Tim James, Commercial Manager, Hamilton Marino Builders NSW (TJ)

  • Nigel Grimshaw, Sales Manager, SBS Group (NG)

  • Roger Weeks, Operations Manager, SBS Group (RW)

*SBS Group now trades as Cortek

The content of this case study is based on statements made by the sources listed above and is a reflection of their views and experience on the above project. Same/similar results are not guaranteed for each user and outcomes may vary across projects.

Discover the advantages of using TRUECORE® steel in your build

Not only are TRUECORE® frames perfect for the projects on The Block but they're versatile and suitable for a range of different builds.

Curved brick building, the facade is supported by light gauge steel framing made from blue TRUECORE steel. It's surrounded by green grass and trees under a clear sky.