Back to Case Studies
April 2019 | 3 min read

SBS Group - Hawthorn Townhouses

SBS Group* delivers in a tight townhouse site

Framing made from TRUECORE® steel helped to reduce the build time on a tight site for the Hawthorn Townhouse development.

Project details


Project

99 Pleasant Road, Hawthorn


Location

Melbourne, Victoria



Show more

Framing made from TRUECORE® steel helped to reduce the build time on a tight site for the Hawthorn Townhouse development.


  • Fast and efficient installation

  • Positive feedback from follow-on trades

  • Overall construction time reduced

  • Lightweight and easy to move around

  • Strong and dimensionally accurate

  • Helped reduce on-site waste

Deliver a three-level townhouse development on a tight site

Project Goal

Key Challenges

  • Limited access to and on site

  • Reducing build time

Key Benefits Delivered

Stephen Compton, Construction Manager, Liberty Builders highlighted the following benefits:

Tight site

Working with SBS Group’s (now trading as Cortek) framing made from TRUECORE® steel meant that even the larger frames could be carried into position on this site by two people, without cranage. (SC)

No need to straighten walls

The precision of framing made from TRUECORE® steel meant that once the frames were in, the team would not be spending lengthy time on site fixing up twisted and warped timber walls, which was a particular consideration on this project, due to its size. (SC)

Reduced costs and time

SBS redesigned the original plans, to substitute a significant amount of structural steel with framing solutions made from TRUECORE® steel, which aided Liberty Builders in terms of both costs and time on site. (CG) In fact, Liberty Builders estimated that the time saved on the structural elements of the build was between 4-6 weeks. (SC)

Reduced on-site waste

With prefabricated frames made from TRUECORE® steel, there is a reduction in waste on site, and the manual handling of the rubbish to remove it from site. (SC)

Ease of managing services

With webs in the floor joists and pre-cut holes in the studs and noggins, it is easier to pass cables and the like through to where you need them. (SC)

Outcomes

“The beauty of working with frames made from TRUECORE® steel is they’re quick, straight, light and generate less onsite mess; we saved 4-6 weeks on the structural element alone.”

Stephen Compton
from Liberty Builders

“We believe that to build faster and easier, we have to be smart about the way we design our framing systems. That’s why we use the analogy of designing with the nail bag on. We approach each project as if we were the builder searching for time, labour and cost savings.”

Caleb Grimshaw
from SBS Group

Sources

  • Caleb Grimshaw, Design Manager, SBS Group (CG)

  • Stephen Compton, Construction Manager, Liberty Builders (SC)

*SBS Group now trades as Cortek

The content of this case study is based on statements made by the sources listed above and is a reflection of their views and experience. Same/similar results are not guaranteed for each user and outcomes may vary across projects.

Discover the advantages of using TRUECORE® steel in your build

Not only are TRUECORE® frames perfect for the projects on The Block but they're versatile and suitable for a range of different builds.

Curved brick building, the facade is supported by light gauge steel framing made from blue TRUECORE steel. It's surrounded by green grass and trees under a clear sky.