Austruss and Manteena Commercial - COVID Surge Centre

Partnering to deliver in five weeks a COVID-19 Surge Centre adjacent to Canberra Hospital.

The facility has been built using prefabricated wall frames and roof trusses made from TRUECORE®steel.

Design versatility
Fast and efficient installation
Overall construction time reduced
Backed by BlueScope
Project Goal

To design and build a 51-bed emergency department within 5 weeks that could be packaged up and repurposed in the future.

Key Benefits Delivered

Design Flexibility

With the floor plan for the structure still being finalised while frame fabrication was underway, design flexibility was key to the success of this project. Says Mr Fowler, “Even as wall frames were being delivered, changes were being made to the floor plan. And the product [TRUECORE® steel] was strong enough to fulfil these changes and adapt to different loadings on the structure.” (AF)

The frames made from TRUECORE® steel allowed for design flexibility. Says Mr Mitton, “The product allowed for flexibility – allowing changes to be made onsite. You take out a few screws, make a few changes and then all of a sudden you’ve got an opening where you didn’t have an opening before” (RM)

Impressive strength-to-weight ratio

Framing made from TRUECORE® steel is structurally very sound, which helped to allow for large spans of ceilings. (RM)

Speed and efficiency

The frames that Austruss made from TRUECORE® steel were produced quickly and designed in a way that they were fast to erect onsite and facilitated the running of services (water pipes, electric cabling, etc.) very easily. (RM)

Consistent quality

Knowing that TRUECORE® steel is a consistent quality product gave Austruss confidence with what they committed to deliver. (AF)

Reliable supply chain

Vital to Austruss turning around the framing so quickly was knowing that enough TRUECORE® steel product was readily available within such a short time frame. (AF)

Project Information
Project

COVID-19 Surge Centre on Garran Oval (access via Canberra Hospital) 

Location

Canberra, ACT

Client
Steel Frame Fabricator
Principal Steel Products

13,400 linear metres of TRUECORE® steel and COLORBOND® steel (fascias, gutters, roof and carport roller doors) 

Project Completion

15 May 2020

Project Details

Construction of the ACT’s temporary COVID-19 Surge Centre was completed on Garran Oval on 15th May 2020, just five weeks from the project’s start date. Local company Aspen Medical, was contracted by the ACT Government to build and operate the 51-bed / 200 staff facility in early April when concerns were high that the current hospital system would be overwhelmed by COVID-19 cases if the virus spread through the Canberra population.

Aspen Medical approached Manteena Commercial to see if they could manage the construction of the facility within five weeks. “Of course. Of course we can” said Rod Mitton, Project Director at Manteena Commercial. Manteena then quickly reached out to long-time partner, Austruss to see if they were on board to build the steel frames.

Working with a 2D drawing of the proposed floor plan, Austruss worked closely with Manteena to design the 51-bed medical structure. With such a limited time to develop a design for the building, Austruss knew that design flexibility was going to be key to the success of the build.

“I made the wall frames telescopic so that they could be extended and decreased as needed. That then meant they could infill different door formats into each frame and slide the door the way that they wanted by just screwing it off where they wanted it once onsite.”

Andrew Fowler, Owner and Managing Director, Austruss Pty Ltd

Austruss was given the go ahead from Manteena on the Tuesday prior to Easter and delivered the first frames to the site on Easter Sunday, thanks to the employees at Austruss committing to working through the weekend for this important cause. Says Mr Fowler, “We are all incredibly proud as a business that we’re involved with a project that is trying to help people.”

The facility has been built using prefabricated wall frames and roof trusses made from TRUECORE® steel, that were manufactured off-site by Austruss. No other materials for the framing were considered. Says Mr Mitton, “We didn’t have any time to explore other options and quite frankly we just knew that the product was right for this project and that’s proven to be the case.”

Outcomes

This project was another success for both Austruss and Manteena who have worked on many projects together since Austruss opened their doors 17 years ago. Says Mr Fowler, “We’ve had a longstanding relationship with Manteena. It comes down to the speed of trust. If you trust people you can get a lot done incredibly quickly.” And the unique circumstances of this project just further cemented their working relationship. “It just adds a new level of trust between both parties,” says Mr Fowler.

Mr Mitton praised Mr Fowler and the Austruss team. “Andrew’s very inventive and if you have an idea or a need, he will come up with a solution. We knew that if Andrew committed to the project, then he would deliver.”

The facility was completed within the 5-week timeframe on 15th May 2020. To ensure maximum mileage the team designed the structure in such a way that it can be packed up into 40-foot containers once it’s no longer needed and transported elsewhere. “It’s designed to be reused again,” says Mr Fowler. “And we complied not just to a temporary design. It can be classed as a permanent building from a structural point of view.” Adding to this, the structure is also built to cyclone standards to account for the helicopter landing deck near the hospital.

When reflecting on the project, and the important part that Austruss played in preparing for a public health emergency, Mr Fowler said, “It always comes down to us having confidence in the products we use. If we didn’t have confidence in TRUECORE® steel to be available and be consistent through the design phase, then we couldn’t have been confident with what we were going to deliver. The consistency of the product and it being readily available and ready to go here in Australia is an important attribute for us.”

Sources
  • Rod Mitton, Project Director, Manteena Commercial
  • Andrew Fowler, Owner and Managing Director, Austruss Pty Ltd

Images courtesy of Aspen Medical and Manteena Commercial.
The content of this case study is based on statements made by the sources listed above and is a reflection of their views and experience. Same/similar results are not guaranteed for each user and outcomes may vary across projects.